Clay Manufacturing: $1M+ Automation Build

Clay Manufacturing: $1.35M Automation Build | Leslie Electrical Services
Clay manufacturing automation control panel build
Case Study

Clay Manufacturing: $1.35M Automation Build

A full-scale automation upgrade for an Australian clay building products manufacturer, turning imported production machinery into a compliant, audit-ready line, delivered end to end by our in-house team.

Industry

Clay Manufacturing Facility

Duration

10 Months

Project Value

$1.35M

Services

Automation, Control Panels, Installation

Want the full write-up?

Download this case study as a PDF to keep or share.
Download PDF
The Situation

Imported machinery that couldn’t legally run

Our client, an Australian clay building products manufacturer, needed a compliant, efficient, and fully modernised clay block production line. The imported machinery for the job arrived outdated, unsafe, and not suitable for commercial use in Australia. It lacked compliant electrical systems, automation capability, safety controls, and production-ready integration, so it couldn’t be legally operated or scaled without a complete transformation.

What We Delivered

A full electrical and automation rebuild, in-house

Designed full production layout and electrical documentation

Built a custom MSB and 5-chamber MCC for power and control

Developed automation for mixing, pressing and pugmill operation

Installed remote I/O and optimised cable routing

Delivered PLd Cat 3 safety systems and machine risk assessment

Implemented a water-reuse system to reduce waste

Provided ongoing reporting and a long-term maintenance plan

The Result

A fully commissioned, audit-ready facility

The finished line is capable of consistent output, with reduced manual handling, improved safety, and automation built to scale, delivered to deadline. As the single contractor on the job, we managed the project end to end: design, panel build, automation, and commissioning, all under one point of contact.

Project Facts
IndustryClay Manufacturing Facility
Duration10 Months
Value$1.35M
DeliverySingle Contractor, End to End
Full Case Study

Get the complete write-up, including project scope and outcomes, as a one-page PDF.

Download PDF
By The Numbers

A production line automated to run reliably at scale

Delivered as a single, accountable project, from design through to a commissioned, compliant production line.

40%+

Efficiency increase through full automation

Reduced manual handling and operational labour costs

Created a scalable platform for future automation upgrades