Food & Beverage: Line Integration

Food & Beverage: Line Integration | Leslie Electrical Services
Food and beverage production line integration works
Case Study

Food & Beverage: Line Integration

A fully integrated production line for an Australian food and beverage facility, built around an irregular floor plan and the client’s existing equipment.

Industry

Food and Beverage

Duration

1 Month

Project Value

$180,000

Services

PLC Automation, CAD Design, Line Integration, Machine Safety

Want the full write-up?

Download this case study as a PDF to keep or share.
Download PDF
The Situation

An ageing line with nowhere to expand

Our client operates a food and beverage processing facility with an irregular, ageing conveyor system spread across a tightly constrained production floor. They needed a fully integrated production line that could work within the limited available space, incorporate existing equipment wherever possible, and lift output without a full plant rebuild.

What We Delivered

A custom-fit line, built around what was already there

Surveyed the existing site and equipment to establish a custom production layout suited to the irregular floor space

Produced detailed CAD drawings to plan the new line configuration before any physical works began

Delivered full PLC automation and control integration across the production line

Engineered safety systems to PLd Category 3, including guarding and interlocking

Integrated existing equipment into the new line design to control project cost and minimise waste

Delivered operator training so the client’s team could run and maintain the new system independently

The Result

More output, same footprint

The client now runs a fully integrated production line that fits their existing floor space and makes use of equipment they already owned. Output increased by 2 tonnes per hour, the layout was optimised for the available space, and the safety system was upgraded to current standards, all delivered within a one month program.

Project Facts
IndustryFood and Beverage
Duration1 Month
Value$180,000
DeliverySingle Contractor, End to End
Full Case Study

Get the complete write-up, including project scope and outcomes, as a one-page PDF.

Download PDF
By The Numbers

A line built for the space it has

Delivered in one month, integrating new automation with equipment already on site.

+2t/hr

Increase in production line output

Full Integration

New line built around existing client equipment

Space-Optimised

Custom layout designed for a constrained floor plan